TENDER RESULTS OF PACKAGE 2,3 AND 4 FOR
220KV, 110KV TRANSMISSION LINES FROM O MON THERMAL POWER PLANT
edf40wrjww2DTV_News:Content_EN
On the official document No. 1539/TTg-CN dated Oct 10th, 2005, The Prime Minister has allowed to adjust the price as well as to approve the result of the tendering package No. 2, 3 and 4 – The 220KV, 110KV transmission lines from O MON Thermal Power Plant.
According to the said document, the successful tenderer of the tendering package No. 2 (Supplying materials-equipment and constructing the transformer station of 220KV, 110KV transmission lines) is awarded to Siemens AG (Germany), this is the kind of “turnkey” contract with the performance time is 26 months; The successful tenderer of the tendering package No. 3 (Supplying spare parts, hanger cable, steel pile, ADSS cable for 220KV, 110KV lines) is awarded to Kalpataru Power Transmission Ltd (India), this is the kind of “all-in” contract with the performance time is 19 months; The successful tenderer of the tendering package No.4 (Constructing the 220KV, 110 KV transmission lines) is awarded to Electrical Installation 3 and Electrical Installation 4 (Vietnam), this is the kind of “adjusted-price” contract with the performance time is 25 months.
By the Prime Minister, The Ministry of Industry was assigned to particularly examine and adjust the price of the said tendering packages and the Board of Director of Electricity of Vietnam was assigned to approve the result of the said tendering packages in order to ensure the price of the contract not to overcome the adjusted-price.
OTHER PROJECTS