SUCCESSFULLY COMPLETION OF 2005 PETROVIETNAM GAS TURNAROUND PROJECT
edf40wrjww2DTV_News:Content_EN
On last Saturday (8/10/2005), at 12:30 p.m, Mustari Maintenance Service and its subcontractors, those are Alpha ECC and Alpha NDT, had officially handed over the GPP DinhCo, at the full operation mode, to the owner, Petrovietnam Gas.
Project was successfully completed within 17days and 02 hours, 02 days earlier against the approved project schedule.
The ealier completion of project was the great effort of all parties participating the project implementation. At the peak period, there were more than 400 Vietnamese engineers, workers and 60 Malaysian expatriates had worked together on site. The project was carried out with the quality, safety and ealier in time.
Together to contribute to the succeed of project, 30 engineers and technicians of Alpha NDT had been involved with the NDT inspection for the whole project, it had carried out both conventional NDT and special tubing inspection like RFECT, MFL, RVI....those are the first time ever happenned in Vietnam. The performance of Alpha NDT was highly appreciated by Certification Company as well as the Project Owner, PETROVIETNAM GAS.
(Pls click on the picture and then next to see PVGAS certificate of completion issued to Alpha NDT)