News


UTM & NDT PROVISION FOR HOANG SA CRANE VESSEL & VSP-05 BARGE MAINTENANCE AND REPAIR

AlphaNDT had provided RT, MT, PT, UT and UTM for the maintenance and repair following requirements of VR-DNV to Hoang Sa Crane Vessel and ABS to VSP-05 Barge.

Read Full Article

ALPHA NDT TO PERFORM NDT FOR TSN AIRPORT AVIATION FUELLING FACILITIES CONSTRUCTION PROJECT

Currently, Alpha NDT have been executing NDT service for TSN Airport Aviation Fuelling Facilities Construction Project which owned by TAPECO and contracted for EPC by WEC ENGINEERS & CONSTRUCTORS PTE LTD. The Project is to construct a new fuel storage facility (3 storage tanks of 3,009 m3 each, thus total depot working capacity being 9,027 m3) and a pipeline connection to the recently-built underground fuel hydrant system here (which include all required airport depot systems, eg unloading/loadi

Read Full Article

ALPHA NDT TO PROVIDE HRD TOPSIDE FABRICATION WITH PAUT SERVICE

Currently, Alpha NDT have supplied PAUT service to HRD Project which owned by ONGC and fabricated by PTSC MC. HRD topside fabrication belongs to Heera Field Development Project of the Owner Oil And Natural Gas Corporation Limited (ONGC), India. This field is offshore located 70 km southwest of Mumbai and remained at an average depth of 50 m below sea level.

Read Full Article

NDT PERFORMANCE FOR VESSEL FABRICATION

urrently, AlphaNDT have been in progress to conduct NDT for vessel fabrication for Su Tu Nau Development project at AlphaECC workshop. The fabrication has been started at the beginning of September for the items of FLARE SCRUBBER (MBF-4321), FLARE SCRUBBER (MBF-4311), HAZADIOUS OPEN DRAIN TANK (ABJ-6211) and HAZADIOUS OPEN DRAIN TANK (ABJ-6221).

Read Full Article

ALPHA NDT TO PROVIDE TLDD HOOK-UP AND COMMISSIONING WITH NDT SERVICES

Alpha NDT just completed NDT provision for Hook-up and Commissioning of Thang Long – Dong Do platform which had been loaded out in July and August 2013 for installation at 01&02/97 Blocks located in Cuu Long Basin, 160 km Vung Tau away from the East.

Read Full Article

TO LOAD OUT THE JACKET SOUTH – SU TU NAU FIELD DEVELOPMENT PROJECT

After 4 months of fabrication, on 2nd September 2013 the jacket South of Su Tu Nau Field Development Project was just loaded out by PTSC SB at its yard, Vung Tau City.

Read Full Article

TO LOAD OUT DONG DO WELLHEAD PLATFORM

Today at PTSC Yard, the main contractor of Thang Long Dong Do Field Development Project, PTSC M&C have organized the load-out ceremony of Dong Do Wellhead Platform after 15 months of fabrication, together with the Thang Long Wellhead platform which had just loaded out at the beginning of July. The WHPs have been installed into two jackets that were built and launched in March 2013 by Vietsovpetro at locations of 01/97 and 02/97 Blocks in Cuu Long Basin. AlphaNDT have been awarded for provision

Read Full Article

TO COMPLETE PLEM & PLET SECTION OF THANG LONG DONG DO FIELD DEVELOPMENT PROJECT

After 7 months of construction, on 17 July the Plem & Plet section of Thang Long Dong Do Field Development project was loaded out at PTSC Yard. This is the subsea template to support the installation of pipeline of the field. AlphaNDT is assigned NDT subcontractor to conduct RT, UT, MT works for the whole fabrication at ECC Yard under supervision of project owner Lam Son JOC.

Read Full Article

NDT SERVICE PROVISION FOR CAMAU FERTILIZER PLANT SHUTDOWN

In July, AlphaNDT have provided NDT services including RT, MT, UTM, PT for the first periodical Shutdown of Camau Fertilizer Plant. Camau Fertilizer Plant was started construction in 2008 and gave the first product in 2011. Camau Fertilizer Plant is invested by Petrovietnam and equipped with the most advanced technology in ammonia and urea manufacture. It is designed to bring onto domestic market the yearly production of 800,000 tonnes of urea as approximated.

Read Full Article
Total : 383 Pages 4/43 : [ 1 ] [ 2 ] [ 3[ 4 ] [ 5 ] [ 6 ] [ 7 ] [ 8 ] [ 9 ] [ 10